LNG Terminal including 4 x 160,000 m³ Tanks

Project Highlights

  • Local codes and standards to be considered and applied where applicable
  • Engineering is executed within several engineering entities of TGE and SNEC

Scope of Work

  • Engineering of complete tank expansion facility
  • Procurement of construction materials and equipment
  • Pre-/Commissioning of expansion facility
  • Construction of complete facility


Project Highlights

4 x 160,000 m³

Storage Capacity

EN 14620-2006

Design Code

Full Containment

Tank Type

4 MTPA

Terminal Capacity

Location

Shenzhen, Guangdong, P.R. China

Owner

CNOOC Shenzhen Gas Co. Ltd.

Contractor

Consortium TGE Gas Engineering GmbH (TGE) and Sinopec Ningbo Engineering Co., Ltd. (SNEC)

Year of Completion

2015

Contract Scope

EPC