LNG Terminal Extension including 1 x 180,000 m³ Tank

Project Description

EPC of the third tank project (one additional 180.000m³ storage tank) as part of the expansion project of the LNG Terminal in Świnoujście in an integrated consortium:

  • Basic and Detail Design LNG storage tank, pumps, interconnecting piping and Boil off gas treatment
  • Procurement of all equipment incl. all mechanical equipment, electrical + instrumentation, safety
  • Procurement of al material incl. special cryogenic material
  • Construction of the storage tank within battery limits
  • Installation of all equipment incl. in-tank pumps and BOG compressors

All Site supervision, construction, commissioning and start-up activities.

Project Highlights

180,000 m³

Storage Capacity

EN 14620

Design Code

Full Containment

Tank Type

LNG

Product

Location

Świnoujście, Poland

Owner

Gaz Systems / Polskie LNG S.A.

Contractor


TGE / PORR SA Consortium

Year of Completion

2024

Contract Scope

EPC