01567 // LNG Terminal | Hammerfest, Norway

Hammerfest, Norway

LNG Terminal including 2 x 125,000 m³ Tanks

Contract Data

Location:

Melkøya Island Hammerfest, Norway

Owner:

Snøhvit License Group, Norway

Contractor:

Consortium TGE – Entrepose – Fabricom

Year of comploetion:

2006

Contract Scope:

EPC

TGE Scope of Work

Basic Engineering

Authority Engineering

Construction

Procurement

Detail Engineering

Comissioning

Terminal & Storage Tank Data

Storage Capacity:

2 x 125,000 m³

Tank Type:

Full containment

Design Code:

BS 7777 / EN 1473

Project Description / Highlights

The project involves the design, engineering, supply, pre-fabrication, installation/ construction and commissioning/ start-up of Storage and Loading Package for LNG, LPG and Condensate (Export Terminal).

The LNG export capacity is designed for 5.6 billion m³ / year.

The project includes 2 LNG storage tanks full-containment type of each 125,000 m³ net capacity, 1 LPG storage tank of 45,000 m³ net capacity and 1 condensate storage tank of 75,000 m³ plus loading facilities for vessels of up to 160,000 m³.