We are very happy to have reached another important milestone in the construction of the 197,000 m³ ethane tank for “Ineos Project One” in Antwerp. 🙌
The outer concrete wall of the tank has been completed on May 17th at 1 am.
Here are some facts about the sliding:
👉 Duration: 339 hours
👉 Concrete Volume: 9,740 m³
👉 Pumping Average Rate: 23,4 m³/h
👉 Average Speed of Sliding: 2,265 m/day
We thank the whole project team for their great work and thank Ineos Belgium for their trust placed in us! 👏👏
Project ONE, is a marquee project within our industry, being the largest petrochemical sector investment in Northern European market within the last 20 years.