Update on construction of Guangdong Energy LNG Terminal!

👉 We are happy to share with you another update on the construction works of our Guangdong Energy Yangjiang LNG Terminal project! 👍

On 28 March 2023, the concrete pouring of the second layer of the central area of the dome of Tank 1# of the Yangjiang LNG Project was successfully completed, which marked the completion of the concrete pouring of the dome of the two tanks of the whole project and the completion of the civil construction of the main body.

Starting from the concrete pouring of the first layer of Tank 2# dome on 12 February 2023, the concrete pouring of the two tank domes has taken a total of 45 days and 5,530m³ of concrete have been poured so far. 👈

Congratulations to the project team! 👏 👏 👏