05794 // LNG Terminal | Yantai Shandong Province

Yantai, Shangdong Province, P.R. China

LNG Terminal including 5 x 200,000 m³ Tank

Contract Data

Location:

Yantai, Shangdong Province, P.R. China

Owner:

Poly-GCL Pan-Asia International Energy (Shangdong) Co., Ltd. 

Contractor:

TGE / CET Consortium

Year of Completion:

2020

Contract Scope:

E

TGE Scope of Work

Preliminary Design

Storage tank pile test scheme

Terminal foundation treatment scheme

Scope of work and technical requirements in EPC ITB

HAZOP, SIL

Terminal & Storage Tank Data

Storage Capacity:

5 x 200,000 m³

Terminal Capacity:

5 MTPA

Tank Type:

Concrete / Steel Full Containment

Design Code:

EN 14620

Project Highlights

Preliminary design for whole LNG Terminal with a turnover capacity of 5 MTPA with 5 x 200,000 m³ LNG tanks and one jetty to berth 80,000 m³ ~270,000 m³ LNG ships in Phase I and consider to reach turnover capacity of 10 MTPA in Phase II